- Approve the agenda renaming "Prestige" to "Financial Statement".
The meeting was called to order at 5:30 PM, beginning with the pledge of allegiance and a moment of silence.
So that there is agreement between board members on the agenda, and the amount of time spent on the meeting, the board shall vote to approve an agenda for the meeting. To the best of its ability, it will follow that agenda, and allow for the chair to move the board through the agenda as specified.
Our Public Comment period is for members of the public to address the board. Each member of the public may sign up to comment at the meeting and will be allotted one minute. The board will listen, but may not directly respond to any comments. Our meetings are open to the public and public record. As such, if your comment is about a private matter, please contact the board via email, or speak to the board chair privately.
For approval
Follow CCSD calendar without changes
Andrew Cilone presenting JICHS monthly Financial Statement.
Change job classification and contract length for Team Associate III (C43) 210-day contract to School Psychologist C45A 190-day contract approval.
Justification for Reclassification
Presented by Leadership Vice Chair, Dr. Tanner Tucker.
Informational
For approval
Presented by Athletic Director Jeremy Holland.
For approval $516,282. plus permitting and electrical drawings.
-Several options were included to change practice field lighting to LED: (Change the entire pole/fixture with a 25-year warranty at $1.5 million, OR retrofit the existing light fixtures for $700k, but only have a 10-year warranty).
-The baseball field was flagged as being the priority field to replace lighting.
-AD Holland will give the Board of Directors two options: One for the entire project, and one for just the Baseball Field.
For approval:$289,500.00
Scope of project:
-Redoing of Practice fields and middle of game field
-Removal of overgrown brush and trees and moving of discuss
-Sodding of areas cleared by above.
The entire project with the multiple vendors will cost $300k.
Quotes to complete the job:
~